據(jù)鉆機(jī)地帶3月7日消息稱(chēng),英國(guó)石油和天然氣公司IOG已經(jīng)完成了其土星銀行項(xiàng)目開(kāi)發(fā)的陸上接收設(shè)施的工作。
這是從英國(guó)北海南部氣田開(kāi)采天然氣的最后一步。也就是說(shuō),IOG表示,土星銀行接收設(shè)施(SBRF)的所有建設(shè)、調(diào)試和功能測(cè)試活動(dòng)都已完成,并已全部簽署。該公司還證實(shí),英國(guó)健康和安全執(zhí)行局要求的澄清已經(jīng)解決。
IOG還表示,啟動(dòng)前的安全審查和操作演練已經(jīng)結(jié)束。這使得該公司及其管道和平臺(tái)運(yùn)營(yíng)商O(píng)DE Asset Management和Bacton終端運(yùn)營(yíng)商Perenco UK完全滿意于2021年3月4日開(kāi)始返輸處理。
該公司解釋道:“返輸是指氣體從終端反向流動(dòng),將管道系統(tǒng)加壓至啟動(dòng)時(shí)的安全操作窗口,在開(kāi)始正向流動(dòng)之前,對(duì)設(shè)備和安全系統(tǒng)進(jìn)行最終功能測(cè)試。受天氣和物流的影響,反氣和開(kāi)井過(guò)程可能需要大約一周的時(shí)間,之后IOG將在陸上迅速收到第一份銷(xiāo)售天然氣。”
IOG首席執(zhí)行官Andrew Hockey表示:“我很高興地說(shuō),陸上土星銀行接收設(shè)施(SBRF)現(xiàn)在已經(jīng)完全投入使用,管道返輸工作已于今天開(kāi)始。”
“這是我們預(yù)計(jì)在大約一周內(nèi)獲得第一批天然氣的最后一步。我要感謝終端運(yùn)營(yíng)商 Perenco,他們非常努力地確保陸上設(shè)施安全并為 IOG 的首次生產(chǎn)做好準(zhǔn)備。”他補(bǔ)充道。
IOG 運(yùn)營(yíng)的土星銀行項(xiàng)目第一期于2019年10月獲得批準(zhǔn)。該油田包括英國(guó)北海南部的Blythe、Elgood和Southwark油田。IOG持有該項(xiàng)目50%的股份,其合作伙伴CalEnergy Resources持有剩余50%的股份。
朱佳妮 摘譯自 鉆機(jī)地帶
原文如下:
IOG North Sea Fields Ready For Start-Up
UK oil and gas firm IOG has completed work on onshore reception facilities for its Saturn Banks project development.
This is the final step to first gas from its Southern North Sea gas fields. Namely, IOG said that all construction, commissioning and function testing activities at the Saturn Banks Reception Facilities (SBRF) were completed and fully signed off. The company also confirmed that the required UK Health and Safety Executive clarifications had been addressed.
IOG also said that the pre-start-up safety review and operations walk-down have been concluded. This enabled the company, its pipeline, and platform operator ODE Asset Management, and Bacton terminal operator Perenco UK to be fully satisfied to begin the backgassing process on March 4, 2021.
“Backgassing involves a reverse flow of gas from the terminal to pressurize the pipeline system up to the safe operating window for start-up, with final function tests of equipment and safety systems before forward flow can begin. Subject to weather and logistics, the backgassing and well start-up sequence is likely to take approximately one week, with first IOG sales gas to be received onshore rapidly thereafter,” the company explained.
“I’m very pleased to say that the onshore Saturn Banks Reception Facilities (SBRF) have now been fully commissioned and pipeline backgassing has started today,” Andrew Hockey, CEO of IOG, stated.
“This is the final step to first gas which we expect in approximately one week. My thanks go to terminal operator Perenco who have worked very hard to ensure the onshore facilities are safe and ready for IOG’s first production,” he added.
The IOG-operated Saturn Banks Project – Phase 1 was sanctioned in October 2019. It consists of Blythe, Elgood, and Southwark fields in the UK Southern North Sea. IOG holds a 50 percent stake in this project and its partner CalEnergy Resources holds the remaining 50 percent.
The project is looking for a gross peak production rate of 140 mmscf/d – 24,000 Boe/d – from gross 2P gas reserves of 302 Bcfe and management estimated 2C gas contingent resources of 132 Bcfe.
免責(zé)聲明:本網(wǎng)轉(zhuǎn)載自其它媒體的文章及圖片,目的在于弘揚(yáng)石化精神,傳遞更多石化信息,宣傳國(guó)家石化產(chǎn)業(yè)政策,展示國(guó)家石化產(chǎn)業(yè)形象,參與國(guó)際石化產(chǎn)業(yè)輿論競(jìng)爭(zhēng),提高國(guó)際石化產(chǎn)業(yè)話語(yǔ)權(quán),并不代表本網(wǎng)贊同其觀點(diǎn)和對(duì)其真實(shí)性負(fù)責(zé),在此我們謹(jǐn)向原作者和原媒體致以崇高敬意。如果您認(rèn)為本站文章及圖片侵犯了您的版權(quán),請(qǐng)與我們聯(lián)系,我們將第一時(shí)間刪除。